NiWest Project

The NiWest Nickel Cobalt Project is regarded as one of the largest and highest quality undeveloped nickel/cobalt resources in Australia. The Project is located in the West Australian Nickel belt, adjacent to Glencore’s Murrin Murrin Nickel-Cobalt Operation.

The region is recognised for its nickel/cobalt production and is well serviced with infrastructure such as public rail linked to ports, gas pipeline, arterial roads, optic fibre communications and long-established mining towns.

The regional rail infrastructure extends to the Malcolm siding near Leonora.  The Murrin Murrin Operation has been serviced from the siding for the past two decades.  An existing commercial airstrip is located at Leonora.

Major imported consumables, including sulphur, are expected to be shipped via the Esperance Port facility and then trucked to site via existing sealed and unsealed roads.  Final saleable products are expected to be trucked to Esperance and then shipped to various customers globally.

NiWest Project Location

GME completed a 12 month Pre-Feasibility Study (PFS) in August 2018.

The PFS presents a stand-alone development pathway for the NiWest Project that incorporates detailed consideration of:

  • The results from the metallurgical test work and engineering conducted on the NiWest Project by GME over the past five years;
  • A review of the various studies conducted by other nickel-cobalt laterite industry participants and the history of underperforming/failed High Pressure Acid Leach (HPAL) laterite nickel developments over the past 20 years; and
  • A review of the nickel and cobalt supply/demand outlooks, including the emerging battery raw materials demand from the EV market.

The selected processing route (refer Simplified NiWest Process Flowsheet diagram) for the PFS involves heap leaching of NiWest ores followed by Pregnant Leach Solution (PLS) neutralisation, Direct Solvent Extraction (DSX) and product crystallisation to produce nickel sulphate hexahydrate (NiSO4.6H2O) and cobalt sulphate heptahydrate (CoSO4.7H2O).

It is noteworthy that successful heap leaching of similar ores has previously been undertaken, at a commercial scale, at the nearby Murrin Murrin Operations. The choice of DSX, validated by extensive prior metallurgical test work, also presents a highly efficient and cost effective pathway to directly produce the nickel and cobalt products specifically sought-after by the high-growth EV battery manufacturing market.

The chosen flowsheet and end product strategy is, in GME’s opinion, the most attractive processing and refining approach after taking into account NiWest’s specific ore characteristics combined with the technical and operating risks, relative capital intensity and final product value of various flowsheet and end product alternatives.

The PFS, including prior test work that commenced in 2013, confirmed that the proposed DSX process flowsheet can treat the NiWest neutralised PLS to generate pure nickel and cobalt electrolytes that can be tailored to the generation of multiple high purity nickel and cobalt products.

The NiWest PFS has confirmed the technical and financial robustness of a long-life operation directly producing high-purity nickel and cobalt sulphate products to be delivered into the forecast rapid growth of lithium-ion battery raw material markets:

Base project parameters

  • Maiden NiWest Ore Reserve estimate of 64.9Mt at 0.91% Ni and 0.06% Co (for 592kt contained nickel and 38kt contained cobalt). Conventional open pit mining at a low projected strip ratio of 2.0:1.
  • Head grades average 1.05% Ni and 0.07% Co for the first 15 years.
  • Selected processing route of heap leaching followed by highly efficient Direct Solvent Extraction (DSX) to produce low-cost nickel and cobalt sulphate products.
  • Initial 27-year operating life at a nameplate processing capacity of 2.4Mtpa. Projected steady-state nickel and cobalt recoveries of 79% and 85% respectively.
  • Total production of 456kt nickel (in nickel sulphate) and 31.4kt cobalt (in cobalt sulphate). Average annual production of 19.2kt nickel and 1.4kt cobalt over the first 15 years.
  • Project construction period of 24 months from Final Investment Decision (FID). Forecast commissioning and plant ramp-up phase of approximately 20 months.

Key economic assumptions and outcomes

  • Life-of-mine metal price estimates of US$8.00/lb nickel (includes US$0.75/lb sulphate premium) and US$25/lb cobalt (zero sulphate premium). A$/US$ assumption of 0.75.
  • Ungeared post-tax NPV8% of A$791M and internal rate of return (IRR) of 16.2% (equivalent pre-tax values of A$1,390M and 21.2%, respectively). Payback period (pre-tax) of 4.4 years.
  • Average cash unit operating cost (post royalties and cobalt credits) of US$3.24/lb contained nickel (US$3.00/lb for the first 15 years).
  • Forecast pre-production capital expenditure of A$966M, representing a globally attractive pre-production capital intensity of sub-US$20 per pound of average annual nickel production.
  • Projected free cashflow (post all capital expenditure and tax) of A$3,342M.
Mt Kilkenny Pit_new logo

Mineral Resource and Ore Reserve Statements

NiWest Mineral Resource Statement

The Company’s Mineral Resource Statement has been compiled in accordance with the Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code 2012 Edition) and Chapter 5 of the ASX Listing Rules and ASX Guidance Note 31.

Mineral Resource Estimate1,2  for NiWest Project at 0.8% Ni Cut-off Grade

Mineral Resource Estimate1,2 for NiWest Project at 1.0% Ni Cut-off Grade

Resource tables

* Columns may not total exactly due to rounding errors. Tonnages are reported as dry tonnage
1  ASX Release 2 August 2018
2  ASX Release 21 February 2017

*  Columns may not total exactly due to rounding errors. Tonnages are reported as dry tonnage
1  ASX Release 2 August 2018
2  ASX Release 21 February 2017

NiWest Ore Reserve Statement

The Company’s Ore Reserve Statement (Table B1) has been compiled in accordance with the Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code 2012 Edition) and Chapter 5 of the ASX Listing Rules and ASX Guidance Note 31.

NiWest Ore Reserve Estimate1 at 0.5% Ni cut-off

*   Columns may not total exactly due to rounding errors. Tonnages are reported as dry tonnage

1  ASX Release 2 August 2018

NiWest Nickel Cobalt Project 

Pre-Feasibility Study August 2018